The project consists of the construction of the following inside Zaatari Camp: - Piping from the Oxfam transmission loop to the storage tanks inlet, around 101 meters, consisting of steel pipes. - On ground water storage reservoir reinforced concrete1,500 cubic meters capacity in District 4. - Pump station civil and yard work in D4, including fencing for the entire tank and pump house area. - On ground water storage reservoir reinforced concrete 300 cubic meters capacity in District 10. - Pump station civil and yard work in D10, including fencing for the entire tank and pump house area. - On ground water storage reservoir reinforced concrete 400 cubic meters capacity in District 11. - Pump station civil and yard work in D11, including fencing for the entire tank and pump house area. - All miscellaneous works, including toilet facilities and rain water drain, to complete the works as per the conditions of the contract specifications.